Report ID:
Single Detached Sample Report
Date:
2/7/2021
Report
Prepared For: John Buyer
Client: John Buyer |
Date: 2/7/2021 | Report ID: Single Detached Sample Report |
Property: 123 Sunny Rd PineTown PA 12345 |
Client's Agent: |
Present at Inspection: Buyer, Buyer's Agent, Buyer's Family Member, Seller's Agent | Approximate age: 25 Years | Structure Style: Colonial |
Temperature: 45 Degrees | Weather: Sunny | Occupancy Status: Occupied, Furnished |
Safety Concern: Denotes an observation, defect or recommendation that is considered an immediate safety concern. Safety standards have increased over the years. The inspector will use today's standards as a baseline to evaluate the home. Safety standards may have changed since your home was built however, it is recommended when ever practical to bring the home up to current standards.
Correction recommended: Denotes a system or component of the home that is deficient or at the end of its service life, and needs corrective action by a professional to assure proper and reliable function. We recommend the professional making any repairs to inspect the property further, in order to discover and repair related problems that were not identified in the report. All evaluations corrections and should be made prior to end of inspection contingency.
Further evaluation recommended: Denotes an observation, defect or recommendation where the full extent of the issue cannot be ascertained in a visual inspection. A more technically exhaustive evaluation or destructive testing may be need to determine the full extent of the issue. All evaluations corrections and should be made prior to end of inspection contingency.
Improvement recommended: Denotes a system or component that should receive normal maintenance, repair, or adjustment in order to continue
functioning properly.
The American Society of Home Inspectors (ASHI): ASHI #261399 |
International Association of Certified Home Inspectors: InterNACHI #15033120 |
Certified Pesticide Applicator: BU13789 Certification #710880 |
PA DEP Radon: Firm #2288 Certification #3356 |
Certified Residential Thermographer: CRT # 2020042407 |
North American Deck & Railing Association (NADRA): Deck Professional - Code Certified |
Method used to Inspect: 32 Foor ladder. Walked Upon roof surface |
Roof Covering Materials: Asphalt Fiberglass Shingles |
Number of layers visible: One layer |
Approximate Age: 1 year |
Average Service Life: 20-30 years |
Gutter Type: 5" K |
Gutter Guards: No |
Method Used to Inspect Attic: Attic access hatch |
Roof Structural Type: Engineered Roof Trusses |
Rafter Board Dimension: 2 X 4, 24 inches on center |
Attic Ventilation Visible: Ridge Vent Soffit Vents Roof Fan |
Attic Insulation Type: Loose-Fill Fiberglass |
Aproxomate R Value: R30 |
Attic Restrictions: Limited Access No Flooring Framing and bracing Low Clearance Insulation |
Exterior Wall Covering Materials: Stucco Stone |
Number of Garage Doors: Three |
Number of Openers: Two |
Photoelectric Eyes: Installed on two doors |
Heating Type: Gas Furnace |
Distribution Method: Duct Work |
Location: Basement |
Approximate Age: 10 years |
Average Service Life: 20-25 years |
Thermostat(s): Dining room |
Heating Type: Gas Furnace |
Distribution Method: Duct Work |
Location: Utility Closet Second Floor |
Approximate Age: 10 years |
Average Service Life: 20-25 years |
Thermostat(s): Master bedroom |
Cooling Type: Central Air |
Distrubution Method: Duct Work |
Location: Basement Exterior-Left side |
Aproximate Age: 15 years |
Average Service life: 15-20 years |
Thermostat: Dining room |
Cooling Type: Central Air |
Distrubution Method: Duct Work |
Location: Exterior-Right side Utility closet second floor |
Aproximate Age: 14 years |
Average Service life: 15-20 years |
Thermostat: Master bedroom |
Hot Water Soure:: Gas Water Heater |
Capacity: 75 Gallon |
Approximate Age: 11 years |
Average Service Life: 9-12 years |
Water Supply System: Municipal Supply |
Water Supply Piping: Copper |
Main Water shut off location: Front of the Basement |
Sewage/Waste System:: Septic System |
Sewage Waste Piping:: PVC |
Service Cable Location: Underground Service Line |
Service Size: 200 AMP |
Panel Type: Circuit breakers |
Main Disconnect: Breaker in panel |
Wiring Method: Romex |
Service Grounding:: Grounding Rod Exterior |
Foundation Stucture: Poured concrete |
Floor Structure: Demensional Joists |
Inspection Restrictions: Wall/Ceiling Coverings Insulation Duct Work and/or Plumbing |
Smoke Detectors: Hard wired with batter back up |
Carbon Monoxide Detectors: No |
Dryer hook up: Gas |
Fireplace: Three Manufactured/Gas Log Set Manufactured/Wood Burning |
Significant areas of chimney flues cannot be adequately viewed during a field inspection, as has been documented by the Chimney Safety Institute of America: "The inner reaches of a flue are relatively inaccessible, and it should not be expected that the distant oblique view from the top or bottom is adequate to fully document damage even with a strong light." Therefore, because our inspection of chimneys is limited to those areas that can be viewed without dismantling any portion of them, and does not include the use of specialized equipment, we will not guarantee their integrity or drafting ability and recommend that they be video-scanned (level two inspection) prior to settlement. Only a level two inspection performed by a CSIA (Chimney safety Institute of America) certified chimney sweep can determine the condition of the flue and if the fireplace is safe to use.
More information about fireplaces and chimneys can be obtained at www.csia.com.
Number of Full Baths: Three |
Number of Half Baths: Two |
Outlets GFCI Protected: Yes |
Stove Cook Top: Gas |
Oven: Electric |
Microwave: Yes |
Dishwasher: Yes |
Garbage Disposal: Yes |
Outlets GFCI Protected: No not all |
This summary list is not intended to be a complete list. There may be other items that are in need of improvement, repair or correction that are not listed here. There may also be improvements that are necessary, but are outside the scope of this inspection.
If any evaluations or corrections are needed, then a professional should inspect the property even further, in order to discover and repair related problems that were not identified in the report. All corrections and evaluations should be made prior to purchasing the property.
The following estimate and repair costs are provided for your convenience. They are not part of you inspection report. The costs are based on HomeTeck Remodeling and Renovation Cost Estimator 2017, and direct input from contractors in the local area.
The costs are given in ranges, as required by the Pennsylvania home inspection law. The actual cost for your home repairs or improvements may be different from the cost listed here.
PEACH Inspections always recommends getting three estimates from contractors who may be performing the work. PEACH Inspections makes no warranty or guarantee as to the correctness or sufficiency of the information contained in this list. PEACH Inspections assumes no responsibility or liability in connection with the use of this list.
3.4 | FLASHINGS | |
. | ||
CORRECTION RECOMMENDED: The flashing detailed called kickout flashing was missing. The flashing detail called a kickout is needed at locations where a roof ends on an exterior wall. The kickout prevents water from running behind the siding/stucco and from streaking down the front of the siding/stucco by diverting it from the roof surface into the gutter. A kick out is needed on the front of the home. A qualified stucco contactor should install the kick out flashings as needed. Need Estimate |
4.2 | VENTILATION FANS | |
. | ||
CORRECTION RECOMMENDED: The attic roof fan was nonfunctional at time of inspection. The fan had power, however when the test button was pushed the fan did not function. A qualified roofing contractor should replace the fan. Need Estimate |
5.2 | DOWNSPOUTS | |
. | ||
CORRECTION RECOMMENDED: The ground drain-line has settled and pulled from the some of the downspouts around the home. The spouts should be re-connected to the drain pipes to prevent water from draining at the home's foundation. A qualified contractor should make the corrections. $150-$200 |
5.4 | DECK/PORCH STRUCTURE | |
. | ||
CORRECTION RECOMMENDED: Wood deterioration was noted at the end of some of the deck boards. This will continue to deteriorate if not repaired or replaced. A qualified contractor should repair or replace as needed. $200-$300 |
||
CORRECTION RECOMMENDED: The deck stair stringer connection is inadequate. The stringers are toe nailed to the header. This connection is not considered strong enough. Toe nailing the stringers to the header does not provide enough lateral strength. Stair stringer connectors should be used to make this connection. A qualified decking contractor should make the corrections. $200-$300 |
||
CORRECTION RECOMMENDED: Wood deterioration was noted at the bottom of the post for the deck stair landing. The posts support the landing. A qualified decking contractor should replace as needed. Need Estimate |
||
CORRECTION RECOMMENDED: The ledger board appears to be attached to the house with nails. No bolts were observed on the ledger board. Deck ledger boards need to be attached directly to the homes band joist with 1/2” galvanized lag bolts and washers or other approved fasteners for this application. There should be a bolt approximately every 16 inches in an alternating high low pattern. A qualified decking contractor should make the corrections. $200-$400 |
||
CORRECTION RECOMMENDED: Corrosion was noted on the joist hangers under the deck. Some of the joist hangers have completely corroded and the joists are no longer being supported by the hangers. A qualified decking contractor should replace the joist hangers as needed. $200-$400 |
||
CORRECTION RECOMMENDED: There is missing flashing along the ledger board of the deck. If water gets behind the ledger board it may weaken the deck to house connection, rot the deck, or water damage to framing of the house. Flashing should have been installed when the deck was built to extend over the top of the ledger board and up behind the exterior finish materials. The flashing should have been installed in shingle like fashion behind any building paper, house wrap or drainage plain that is behind the exterior finish materials. A qualified contractor should install flashing to prevent water from running behind the ledger board. However, with a stucco exterior this may be difficult if not impractical to do after the deck has been built. If the flashing is not installed the joint between the deck and the house should be sealed with a good exterior sealant (caulking) and the joint should be monitored and maintained as necessary. $50-$100 to seal joint |
5.8 | WINDOWS | |
. | ||
CORRECTION RECOMMENDED: Deteriorated wood was noted on the window frames and/or sills on the rear side of the home. This can allow water intrusion and will continue to deteriorate if not repaired or replaced. A qualified contractor should repair or replace as needed. Need Estimate |
5.9 | EAVES, SOFFITS AND FASCIAS | |
. | ||
CORRECTION RECOMMENDED: Wood damage/deterioration was noted on the fascia boards left side of the house. A qualified contractor should repair or replace as needed. $200-$400 |
8.0.A | AIR CONDITIONING SYSTEM | |
. | ||
The central air conditioning was not operationally tested during this inspection. There may be deficiencies with the system that are in need of repair or correction
that the inspector was unable to verify. Most manufacturers of air conditioning systems recommend that these units not be tested if the ambient temperature for the
previous 24 hours is below 60° F to avoid damaging the compressor. It is recommended that a service company check the unit when ambient temperatures permit.
If this is during the winter months and temperatures are not expected to rise to this level there is an alternative option. If there are any concerns you may wish to
contact a qualified licensed HVAC contractor, who can bring special equipment to heat up the crankcase of the compressor in order to safely test the equipment.
This method of testing is beyond the scope of this visual inspection.
|
8.0.B | AIR CONDITIONING SYSTEM | |
. | ||
The central air conditioning was not operationally tested during this inspection. There may be deficiencies with the system that are in need of repair or correction
that the inspector was unable to verify. Most manufacturers of air conditioning systems recommend that these units not be tested if the ambient temperature for the
previous 24 hours is below 60° F to avoid damaging the compressor. It is recommended that a service company check the unit when ambient temperatures permit.
If this is during the winter months and temperatures are not expected to rise to this level there is an alternative option. If there are any concerns you may wish to
contact a qualified licensed HVAC contractor, who can bring special equipment to heat up the crankcase of the compressor in order to safely test the equipment.
This method of testing is beyond the scope of this visual inspection.
|
10.2 | FIRE SPRINKLERS | |
. | ||
FURTHER EVALUATION RECOMMENDED: The fire sprinkler system is an Anti Freeze system. The function and adequacy of the fire sprinkler system is beyond the scope of the inspection. Determining if the fire sprinkler system meets current standards is beyond the scope of this inspection. However there may be known deficiencies observed by the inspector that will be noted in the report. Anti Freeze fire sprinkler systems require routine service, approximately every couple years. The anti freeze needs to be flushed from the system and replaced periodically. The local municipality may have certain regulations pertaining to the servicing of the fire sprinkler system. There is no visible service record on the systems. Recommend asking the sellers when the system was last serviced. If no records or records not up to current service period recommend the system be serviced by a qualified sprinkler company prior to end of inspection contingency. Needs Further Evaluation |
11.0 | ELECTRICAL METER | |
. | ||
CORRECTION RECOMMENDED: The grounding rod was installed to high. The grounding rod is sticking up out of the ground about 34 inches. Grounding rods are 8 ft. long and should be installed with only a small portion of the rod sticking out of the ground. Improperly installed grounding rods reduces the effectiveness of the ground. Corrections should be made by a qualified electrician. $100-$200 |
11.1 | MAIN ELECTRICAL PANEL | |
. | ||
CORRECTION RECOMMENDED: Two circuits were observed within the main electrical panel doubled up (referred to as a “double tap”). A double tap is when two circuit wires are connected to only one breaker. The circuits should be separated so that each circuit is serviced by its own circuit breaker. A qualified electrician should make the necessary corrections. $150-$300 |
11.2 | ELECTRICAL WIRING | |
. | ||
CORRECTION RECOMMENDED: There was an open junction box in the basement. All junction boxes should have covers on them to protect the electrical splices inside them from coming undone and from coming in contact with people or objects. Wires coming into a junction box should be clamped to the box to prevent them from being pulled apart. Recommend having a qualified person install cover plate on junction box. 0-$50 |
12.2 | FOUNDATION | |
. | ||
ASK THE SELLER: At the time of the inspection there were no signs of active water intrusion in the basement. The basement appeared dry.
Recommend asking the seller the extent of water leakage, accumulation or dampness there is within the basement. In the short time of this inspection, it is impossible to determine prior or future water penetration problems. Conditions that affect the basement’s dryness (weather, wind, and temperature) will vary greatly during the course of a year. Recommend referring to the sellers disclosure form to determine if the sellers are aware of any water leakage, accumulation, or dampness in the basement. Ask Seller about item |
13.0 | DOORS | |
. | ||
CORRECTION RECOMMENDED: The front middle bedroom door was rubbing/hitting the door frame. Unable to shut properly. The door needs adjusting. A qualified contractor should repair as needed. $75-$150 |
13.1 | WINDOWS | |
. | ||
CORRECTION RECOMMENDED: Unable to open the front window in the en suite. The window appeared stuck shut. A qualified contractor should further evaluate and repair as needed. Needs Further Evaluation |
||
CORRECTION RECOMMENDED: Wood deterioration was noted on the window sills in the rear left room on the first floor. This will continue to deteriorate and may lead to water intrusion if not repaired or replaced. A qualified window contractor should repair or replace as needed. Need Estimate |
||
CORRECTION RECOMMENDED: Fogged windowpanes were noted, 2 total. Windows in the following locations needed repair: Rear left room first floor. In order to correct the fogged appearance of the glass, a replacement of the glass pane or the window sash will be necessary. A qualified window contractor should repair or replace as necessary. $150-$300 each |
14.2 | TUBS & SHOWERS | |
. | ||
CORRECTION RECOMMENDED: Open grout lines were observed at the tub/shower wall in the en suite. Open grout lines can allow water to penetrate behind the tub/shower wall and lead to moisture damage. A qualified contractor should repair as needed. $200-$300 |
||
Master shower stall had no valve handles at time of inspection. Unable to test shower. A qualified plumber should install valve handles as needed. Recommend verifying shower functions properly prior to settlement. |
14.4 | OTHER BATHROOM COMPONETS | |
. | ||
CORRECTION RECOMMENDED: The bathroom fans were observed venting into the attic. The fans should be vented to the outside. Currently the fans vent moisture into the attic space. This moisture can reduce the R-value of the insulation. The moisture can contribute to mold growth on the underside of the roof sheathing. A qualified contractor should vent the fans to the exterior. $300-$500 |
11.3 | GFCI PROTECTION | |
. | ||
SAFETY CONCERN: The receptacle left of the basement bar sink should be GFCI protected. All receptacles that are within six feet of a water source should be GFCI protected. $75-$150 |
13.0 | DOORS | |
. | ||
SAFETY CONCERN: One or more exterior egress doors use "keyed dead bolt locks " on the inside. Although commonly used for security purposes, this is not the best practice. For safety purposes in case of fire, all exterior locks on egress doors should be thumb latched on the inside. Recommend having a qualified person change keyed dead bolts to thumb latched dead bolts for safety purposes. $75-$150 |
13.4 | SMOKE & CARBON MONOXIDE DETECTORS | |
. | ||
SAFETY CONCERN: No carbon monoxide detectors were found in the home. Today's standards for carbon monoxide detectors is to have one installed outside of
each separate sleeping area in the immediate vicinity of the bedrooms in homes which have fuel-fired appliances and/or homes that have attached garages. For
increased safety I recommend installing at least one carbon monoxide detector in the second floor hall way.
$75-$150 |
13.5 | LAUNDRY | |
. | ||
SAFETY CONCERN: The receptacle above the washer and dryer should be GFCI protected. All receptacles that are within six feet of a water source should be GFCI protected. Recommend having a qualified electrician install GFCI protected receptacle. $100-$200 |
15.5 | OUTLETS | |
. | ||
SAFETY CONCERN: Not all of the kitchen receptacles that service the kitchen countertops were GFCI protected. The receptacle right of the stove are not GFCI protected. All receptacles that serve the kitchen countertops should be GFCI protected. Recommend having a qualified electrician install GFCI receptacles as needed. $75-$150 |
ATTENTION: This inspection report is incomplete without reading the information included herein at these links/attachments. Note If you received an emailed PDF version of this page and did not receive a copy of the report through the internet please contact your inspector for a PDF copy of the attachments.
I carefully walked upon the roof surface. The asphalt fiberglass shingles on the roof appear to be in functional condition.